exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 587 discussion

Actual exam question from PMI's PMP
Question #: 587
Topic #: 1
[All PMP Questions]

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.
What does the project manager need to do first in order to have good project performance?

  • A. Coach those team members lacking hybrid knowledge to learn on the job.
  • B. Change the team to include hybrid experts.
  • C. Assess the required training per team member.
  • D. Deliver hybrid training to all team members.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: C
just having some member lack hybrid knowlege so the first thing PM need to assess to indentify the needed for each member and then make the plan traning and coach them
upvoted 2 times
...
xcjxcj
1 year, 4 months ago
Selected Answer: A
A. Not comfortable with C which all team members are assessed.
upvoted 1 times
...
futbool10
1 year, 5 months ago
C. The question is what needs to do first. Assessing comes first before coaching team member. Notice how the answer could pivot to A if the question is "what needs to do" without the "first".
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: C
C. Assess the required training per team member
upvoted 1 times
...
randomname123
1 year, 10 months ago
Selected Answer: C
Need to find out what each team member knows first. C is the way to find out who would need answer A.
upvoted 2 times
...
[Removed]
1 year, 11 months ago
Selected Answer: A
If only some team members do not have the knowledge then it makes sense to train them. Thoughts?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...