A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches. What does the project manager need to do first in order to have good project performance?
A.
Coach those team members lacking hybrid knowledge to learn on the job.
just having some member lack hybrid knowlege so the first thing PM need to assess to indentify the needed for each member and then make the plan traning and coach them
C. The question is what needs to do first. Assessing comes first before coaching team member. Notice how the answer could pivot to A if the question is "what needs to do" without the "first".
If only some team members do not have the knowledge then it makes sense to train them. Thoughts?
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
DavidTri
10 months, 2 weeks agoxcjxcj
1 year, 4 months agofutbool10
1 year, 5 months agovictory108
1 year, 8 months agorandomname123
1 year, 10 months ago[Removed]
1 year, 11 months ago