You are the project manager of the NHG. The following figure represents your project network diagram.
Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect
Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?