Question #: 176
Topic #: 1
[All PMP Questions]

The scope of a project is to replace the street signs within a 10-km radius. The client does not want to sign the project closure report if the radius is not extended by 1 km, to be aligned with the council's development plan.
What should the project manager do?

  • A. Delay the approval and ask the project sponsor for additional funding.
  • B. Contact the council and ask for their approval to extend the scope of the project.
  • C. Initiate a new project and discuss the request because it came in too late.
  • D. Obtain formal acceptance for the completed work and submit a change request.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Rezaee
9 months, 3 weeks ago
Selected Answer: D
D. Obtain formal acceptance for the completed work and submit a change request:
upvoted 1 times
...
Asakthi
1 year, 3 months ago
D. Obtain formal acceptance for the completed work and submit a change request.
upvoted 1 times
...
victory108
1 year, 5 months ago
Selected Answer: D
D. Obtain formal acceptance for the completed work and submit a change request
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...