A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?

  • A. Ask the customer to reduce the backlog to meet the launch date.
  • B. Increase the capacity of the team to deliver the completed backlog on time.
  • C. Assist the team in defining a minimum viable product (MVP) by the launch date.
  • D. Schedule a meeting with the stakeholders to review the contingency plan.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PMNoel
7 months ago
Selected Answer: C
Answer is C
upvoted 1 times
...
deeps2023
9 months ago
why not A
upvoted 1 times
...
SteAle
10 months, 1 week ago
Selected Answer: C
C. Assist the team in defining a minimum viable product (MVP) by the launch date.
upvoted 2 times
...
victory108
10 months, 3 weeks ago
Selected Answer: C
C. Assist the team in defining a minimum viable product (MVP) by the launch date
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago