A project manager is leading a team that is geographically dispersed. The team needs to collaborate and finalize the monthly reports. Occasionally, meetings occur during the weekends due to the time differences. Team members have expressed that they do not want to work on the weekends.
What should the project manager do?
Aditech
3 weeks agoKennyMuffins
3 months agoAbdelmonm
3 months ago125bb38
3 months, 1 week agoOnly12go
6 months, 2 weeks agoDavid983
6 months, 2 weeks agovictory108
7 months, 1 week agoAish_
9 months agoTONYJAVI
9 months, 1 week agorandomname123
9 months, 4 weeks agoaqz_111
10 months, 1 week agoJamrock
8 months, 1 week ago