exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 207 discussion

Actual exam question from PMI's PMP
Question #: 207
Topic #: 1
[All PMP Questions]

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project.
Which action should the project manager take?

  • A. Facilitate a supportive level of engagement for this stakeholder.
  • B. Ask the project sponsor for advice as it might be possible to work with another stakeholder.
  • C. Perform a qualitative risk analysis using a probability and impact matrix.
  • D. Ensure the key information is accurate and monitor the situation as the project progresses.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
9 months ago
Selected Answer: A
A. Facilitate a supportive level of engagement for this stakeholder
upvoted 1 times
...
victory108
1 year ago
Selected Answer: A
A. Facilitate a supportive level of engagement for this stakeholder
upvoted 1 times
...
SteAle
1 year ago
Selected Answer: A
Since this stakeholder is important for the project being responsible for providing key information to the team, the PM should improve the stakeholder's level of support
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...