During the sprint planning of a project, the team members have a disagreement about the comparative size of the backlog items and if they would fit into the next sprint. Considering a hybrid approach, what should the project manager do?
A.
Ask an external technical leader to provide input and plan the sprint.
B.
Remove the items from the product backlog since the size couldn't be estimated.
C.
Facilitate the discussion so that the team members can reach a consensus.
D.
Make the decision about the backlog items based on what makes more sense.
Conflict Management is one the responsibilities of a PM
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Lucky_Cindy
7 months agovictory108
10 months, 2 weeks agoSteAle
11 months ago