exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 222 discussion

Actual exam question from PMI's PMP
Question #: 222
Topic #: 1
[All PMP Questions]

During the sprint planning of a project, the team members have a disagreement about the comparative size of the backlog items and if they would fit into the next sprint.
Considering a hybrid approach, what should the project manager do?

  • A. Ask an external technical leader to provide input and plan the sprint.
  • B. Remove the items from the product backlog since the size couldn't be estimated.
  • C. Facilitate the discussion so that the team members can reach a consensus.
  • D. Make the decision about the backlog items based on what makes more sense.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: C
C. Facilitate the discussion so that the team members can reach a consensus
upvoted 1 times
...
victory108
10 months, 2 weeks ago
Selected Answer: C
C. Facilitate the discussion so that the team members can reach a consensus
upvoted 1 times
...
SteAle
11 months ago
Selected Answer: C
Conflict Management is one the responsibilities of a PM
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...