Actual exam question from PMI's PMP
Question #: 225
Topic #: 1
[All PMP Questions]

A project manager is leading an automation project. The project team is colocated and includes people from both the technical and business units. The project manager discovers that personal differences and work styles are affecting the project negatively.
How should the project manager address this?

  • A. Develop a schedule that ensures people with personal differences work separately.
  • B. Invite the functional managers of the different units to address their personal differences.
  • C. Use an approach to the project that does not involve colocation.
  • D. Meet with the team and agree on expectations from team members.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: D
D. Meet with the team and agree on expectations from team members.
upvoted 1 times
...
Asakthi
9 months, 2 weeks ago
D. Meet with the team and agree on expectations from team members.
upvoted 1 times
...
victory108
10 months, 2 weeks ago
Selected Answer: D
D. Meet with the team and agree on expectations from team members
upvoted 1 times
...
SteAle
11 months ago
Selected Answer: D
Setting expectations and defining ground rules are the vital ingredients of a high-performing team
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...