A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility, Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.
What should the project manager do next?

  • A. Perform a cost-benefit analysis to evaluate using the Point B option.
  • B. Add the issue to the change log and request additional budget through the change control board (CCB).
  • C. Seek a decision from the construction team after explaining the project budget and schedule constraint.
  • D. Use the Point B option because it will save the project cost and time.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: A
A. Perform a cost-benefit analysis to evaluate using the Point B option
upvoted 2 times
...
victory108
10 months, 2 weeks ago
Selected Answer: A
A. Perform a cost-benefit analysis to evaluate using the Point B option
upvoted 1 times
...
SteAle
11 months ago
Selected Answer: A
A PM should always perform an analysis prior to taking any actions.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...