A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?

  • A. Provide the failed test results along with the agreed-upon acceptance criteria.
  • B. Share unsuccessful results from previous projects with a similar scope.
  • C. Document in the risk log that the issues in the system were already identified.
  • D. Show that the acceptance criteria were changed by the vendor without approval.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: A
A. Provide the failed test results along with the agreed-upon acceptance criteria
upvoted 1 times
...
victory108
10 months, 2 weeks ago
Selected Answer: A
A. Provide the failed test results along with the agreed-upon acceptance criteria
upvoted 1 times
...
SteAle
11 months ago
Selected Answer: A
Provide the failed test results along with the agreed-upon acceptance criteria as a evidence
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...