Actual exam question from PMI's PMP
Question #: 241
Topic #: 1
[All PMP Questions]

A project manager received a request to add features and functions to the project after the scope had already been established.
What should the project manager do?

  • A. Follow the requirements management process.
  • B. Follow the stakeholder engagement process.
  • C. Follow the risk management process.
  • D. Follow the change management process.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
andrologin
3 months, 1 week ago
Selected Answer: D
All changes should go through change request process
upvoted 1 times
...
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
SteAle
10 months, 2 weeks ago
Selected Answer: D
Review the change mgmt plan to understand how to deal with changes
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago