A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
A.
Delegate other team members to complete this team member's tasks.
B.
Mentor the team member and provide the necessary training.
C.
Request the team member to move to another team.
D.
Include the team member in an improvement program through a human resources (HR) request.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Lucky_Cindy
7 months agovictory108
9 months, 3 weeks agoSteAle
10 months, 4 weeks ago