A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project.
What should the project manager do in this situation?

  • A. Delegate other team members to complete this team member's tasks.
  • B. Mentor the team member and provide the necessary training.
  • C. Request the team member to move to another team.
  • D. Include the team member in an improvement program through a human resources (HR) request.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: B
B. Mentor the team member and provide the necessary training
upvoted 1 times
...
victory108
9 months, 3 weeks ago
Selected Answer: B
B. Mentor the team member and provide the necessary training
upvoted 1 times
...
SteAle
10 months, 4 weeks ago
Selected Answer: B
The PM should support & mentor the team member
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...