Exam PMP topic 1 question 268 discussion

Actual exam question from PMI's PMP
Question #: 268
Topic #: 1
[All PMP Questions]

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later, the client sends a list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.
What should the project manager have done to prevent this from happening?

  • A. Reviewed the acceptance criteria and obtained client approval.
  • B. Allocated a risk budget for any post-release improvements.
  • C. Conducted a pilot to understand the client's performance parameters.
  • D. Established meetings with the client throughout the project phases.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
11 months, 2 weeks ago
Selected Answer: A
A. Reviewed the acceptance criteria and obtained client approval
upvoted 1 times
...
SteAle
1 year ago
Selected Answer: A
Close project or phase process activity: Confirming the delivery and formal acceptance of deliverables by the customer;
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...