A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused
10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
Lucky_Cindy
7 months agoOnly12go
7 months, 1 week agoAlizade
8 months agovictory108
9 months, 3 weeks agosmartrammy
10 months, 3 weeks agoSteAle
10 months, 4 weeks agoSteAle
10 months, 4 weeks ago