exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 273 discussion

Actual exam question from PMI's PMP
Question #: 273
Topic #: 1
[All PMP Questions]

A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused
10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?

  • A. Reassure the sponsor by explaining the probability of this risk materializing is extremely low.
  • B. Carry out tests to verify that the system does not fail again due to the high occurrence of events.
  • C. Review the list of risks to verify that this issue was considered and execute the detailed action plan.
  • D. Inform the sponsor about the issue and make a request for sufficient funds to be made available.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: C
C. Review the list of risks to verify that this issue was considered and execute the detailed action plan
upvoted 1 times
...
Only12go
7 months, 1 week ago
Selected Answer: C
C. Review the list of risks to verify that this issue was considered and execute the detailed action plan. In this situation, the project manager should first review the project's risk management plan and the list of identified risks to determine if this specific risk was previously considered. If it was, the project manager should check the detailed action plan associated with this risk. If there are already actions and mitigation strategies in place, the project manager should ensure that these actions are executed and that the issue is being addressed according to the established plan.
upvoted 2 times
...
Alizade
8 months ago
Selected Answer: C
The correct answer is: C. Review the list of risks to verify that this issue was considered and execute the detailed action plan.
upvoted 1 times
...
victory108
9 months, 3 weeks ago
Selected Answer: C
C. Review the list of risks to verify that this issue was considered and execute the detailed action plan
upvoted 1 times
...
smartrammy
10 months, 3 weeks ago
Selected Answer: C
C. Review the list of risks to verify that this issue was considered and execute the detailed action plan.
upvoted 2 times
...
SteAle
10 months, 4 weeks ago
Selected Answer: A
C. Review the list of risks to verify that this issue was considered and execute the detailed action plan.
upvoted 2 times
SteAle
10 months, 4 weeks ago
mistake - I've have voted for Answer C
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...