A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.
What should the project manager do next?

  • A. Discuss this issue with the affected team members and support them during the transition.
  • B. Start looking for replacements as soon as possible to help prevent any schedule slippage.
  • C. Engage with the project sponsor to ensure that this change does not affect the project execution.
  • D. Determine the impact to the project and implement mitigations per the project management plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: D
D is correct
upvoted 1 times
...
victory108
9 months, 3 weeks ago
Selected Answer: D
D. Determine the impact to the project and implement mitigations per the project management plan
upvoted 1 times
...
SteAle
10 months, 4 weeks ago
Selected Answer: D
Risk Mgmt Plan is part of the Project Management Plan. It is clearly a risk that needs to be assess following the predefined approach
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...