exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 299 discussion

Actual exam question from PMI's PMP
Question #: 299
Topic #: 1
[All PMP Questions]

A project manager is using a subcontractor for mobile application development. When the project team tests the application, they realize it does not comply with the new company user-interface standards. Even though these new standards were not included in the statement of work (SOW), the subcontractor agrees to the additional scope as long as payment for this additional work is paid immediately.
What should the project manager do?

  • A. Negotiate new pricing based on the revised estimations from the subcontractor that reflect the new work.
  • B. Initiate a change request and review the contract to evaluate the payment options before responding.
  • C. Deny the subcontractor's payment request, because the product does not comply with the project needs and close the project.
  • D. Initiate a change to incorporate an immediate payment milestone in the contract as per the subcontractor's request.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: B
B. Initiate a change request and review the contract to evaluate the payment options before responding
upvoted 1 times
...
victory108
9 months, 1 week ago
Selected Answer: B
B. Initiate a change request and review the contract to evaluate the payment options before responding
upvoted 1 times
...
SteAle
10 months, 3 weeks ago
Selected Answer: B
Change in the scope requires a CR. However, before including an immediate payment milestone in the contract, it makes sense to evaluate possible payment options.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago