A project manager is managing a government project that targets the development of small businesses in remote towns. The project team is having difficulty conducting entrepreneurship training in some of the targeted towns because the local municipal governments will not authorize the training. As a result of the delay, project implementation is at risk.
What is a probable reason for this?

  • A. The project should have constructed training centers in the remote towns.
  • B. The project did not identify and engage the correct stakeholders.
  • C. The project did not fully engage the project sponsor.
  • D. The project should have representatives in all the remote towns.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 4 weeks ago
Selected Answer: B
B. The project did not identify and engage the correct stakeholders
upvoted 1 times
...
victory108
9 months, 1 week ago
Selected Answer: B
B. The project did not identify and engage the correct stakeholders
upvoted 1 times
...
SteAle
10 months, 3 weeks ago
Selected Answer: B
The local municipal governments should have been identified and engaged as the key stakeholders
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...