exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 326 discussion

Actual exam question from PMI's PMP
Question #: 326
Topic #: 1
[All PMP Questions]

A company plans to initiate a project involving a new technology. Approval for the project is required.
What should the project manager do?

  • A. Review the cost and schedule baselines for execution.
  • B. Define change management for the new technology.
  • C. Identify the risks in implementing the new technology.
  • D. Analyze the cost and identify the project benefits.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 month ago
Selected Answer: D
this is in the initialize state, so A: no baseline, its on executing B: same no change ,its on planning C: not sure if it has been approve >> D: how much it need and how much we can gain>> ok
upvoted 1 times
...
Lucky_Cindy
6 months, 1 week ago
Selected Answer: D
D. Analyze the cost and identify the project benefits
upvoted 1 times
...
Alizade
7 months, 2 weeks ago
Selected Answer: D
D. Analyze the cost and identify the project benefits
upvoted 1 times
...
victory108
8 months, 3 weeks ago
Selected Answer: D
D. Analyze the cost and identify the project benefits
upvoted 1 times
...
SteAle
10 months, 1 week ago
Selected Answer: D
Step # 1 - Prepare a business case
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago