A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change.

What should the project manager do?

  • A. Seek advice from the legal department and implement penalties.
  • B. Search for a new supplier that can deliver the same materials on time.
  • C. Tell the supplier that they have an obligation to supply the raw material.
  • D. Assess the possible impact of the raw material shortage on the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: D
D. Assess the possible impact of the raw material shortage on the project
upvoted 1 times
...
mdadewale
10 months ago
D is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago