exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 176 discussion

Actual exam question from PMI's CAPM
Question #: 176
Topic #: 1
[All CAPM Questions]

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

  • A. Early requirements gathering
  • B. Feedback analysis
  • C. Progressive elaboration
  • D. Requirements documentation
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
4 days, 22 hours ago
Selected Answer: C
Why the other options are incorrect: A. Early requirements gathering: Happens at the start of the project. In this case, the refinement is happening after prototyping. B. Feedback analysis: Is a general term and could be part of the process, but it’s not the recognized project management technique being described. D. Requirements documentation: Refers to the process of formally recording requirements, not refining them through testing and iteration.
upvoted 1 times
...
041ba31
1 year ago
Selected Answer: C
C. Progressive elaboration The team is using the technique of "progressive elaboration." Progressive elaboration is a project management technique that involves continuously refining and expanding project details and requirements as more information becomes available throughout the project's lifecycle. In this scenario, the team initially created a prototype of the drone and sent it to the customer for testing. Based on the feedback received from the customer, the team used that information to refine and expand the project requirements. This iterative process of refining and expanding project details is an example of progressive elaboration, which is commonly used in agile and adaptive project management approaches to accommodate changing customer needs and project insights.
upvoted 2 times
...
[Removed]
1 year, 5 months ago
Selected Answer: C
Page 715, PMBOK 6th Edition The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available. Risks and costs are reduced when this is used.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...