Exam PMP topic 1 question 725 discussion

Actual exam question from PMI's PMP
Question #: 725
Topic #: 1
[All PMP Questions]

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

  • A. Contact the vendor that supplied similar equipment for a previous project.
  • B. Use the existing equipment and replace it later with the new equipment.
  • C. Ask the project sponsor to expedite the vendor selection process.
  • D. Work with the procurement team to find alternative options.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
10 months ago
Selected Answer: D
D. Work with the procurement team to find alternative options
upvoted 2 times
...
SteAle
1 year ago
Selected Answer: D
Before going to the sponsor for help, the PM needs to try find a solution by himself
upvoted 2 times
...
SynikalDemon
1 year ago
Not sure if it C or D, but I think C fits best.
upvoted 1 times
...
Kayyyy
1 year ago
Selected Answer: C
why not C?
upvoted 1 times
ChezQW
9 months, 2 weeks ago
They should see if there are any viable alternative before coming up with a solution.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...