An agile team is brainstorming end prioritizing all of the risks according to severity.

What should the teem do about the identified risks?

  • A. Mitigate the risks that are applicable to the current and following iterations.
  • B. Focus on the project deliverables rather than the documented risks.
  • C. Agree that any issue can be handled when it becomes a problem.
  • D. Acknowledge that the risks will be handled in the corresponding iteration.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 4 weeks ago
Selected Answer: A
A. Mitigate the risks that are applicable to the current and following iterations
upvoted 1 times
...
ziyaetuk
10 months ago
A. In an agile environment, risks are typically managed in an iterative manner, with the team focusing on those risks that are most relevant to the work at hand and potentially the work in the next iteration. This is because the agile approach values responding to change over following a plan. By mitigating the risks that apply to the current and following iterations, the team can effectively manage risk while remaining flexible and adaptable.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago