exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 382 discussion

Actual exam question from PMI's PMP
Question #: 382
Topic #: 1
[All PMP Questions]

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months.
What should the project lead do next?

  • A. Work with the agile team to schedule the incremental deliveries to enable delivery of business value sooner to the customer.
  • B. Work with the stakeholder to understand what the concerns are while, at the same time, conveying the benefits of incremental deliveries.
  • C. Schedule meetings with the customer to determine their ability to support multiple incremental deliveries.
  • D. Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: B
B. Work with the stakeholder to understand what the concerns are while, at the same time, conveying the benefits of incremental deliveries
upvoted 1 times
...
victory108
9 months ago
Selected Answer: B
B. Work with the stakeholder to understand what the concerns are while, at the same time, conveying the benefits of incremental deliveries
upvoted 1 times
...
SteAle
10 months, 2 weeks ago
Selected Answer: B
The senior business stakeholder seems to be unaware of the iterative approach's benefits, hence the PM needs to understand his concerns and educate him about the benefits
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...