A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain.
What should the project manager do now?

  • A. Reclassify low-level risks as high-level risks.
  • B. Notify stakeholders that all high-level risks have been resolved.
  • C. Reduce the priority of project risks as all remaining risks are low-level.
  • D. Reevaluate identified risks and update the risk register.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SteAle
Highly Voted 10 months, 2 weeks ago
Selected Answer: D
D. Reevaluate identified risks and update the risk register. - no risks should be left out, even the low-priority ones. Plus, some of these risks might have changed, so defo worths reevaluting them
upvoted 6 times
...
Lucky_Cindy
Most Recent 6 months, 3 weeks ago
Selected Answer: D
D. Reevaluate identified risks and update the risk registe
upvoted 1 times
...
victory108
9 months ago
Selected Answer: D
D. Reevaluate identified risks and update the risk registe
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...