A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?

  • A. Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.
  • B. Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue.
  • C. Delay the project until the issue is addressed and no longer presents as a risk to the project.
  • D. Inform the sponsor that the issue has arisen and that the project's success may be uncertain.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: B
B is correct
upvoted 1 times
...
victory108
9 months ago
Selected Answer: B
B. Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue
upvoted 1 times
...
SteAle
10 months, 2 weeks ago
Selected Answer: B
B is the obvious choice. The issue needs to be addressed, hence the PM needs to arrange a meeting with the relevant stakeholders to work out a plan/solution.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...