A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project. Which activity should be considered as a priority?
A.
Release the resources and plan for a project completion celebration.
B.
Ensure that knowledge transfer activities are executed as planned.
C.
Hold a steering committee meeting to inform them of the project completion.
D.
Mark the product backlog completion status and update the communications management plan.
Google Bard: "The answer is B. Ensure that knowledge transfer activities are executed as planned.
Knowledge transfer is the process of transferring knowledge from one person or group to another. It is an important part of project closure because it ensures that the knowledge gained during the project is not lost.
The other options are also important, but they are not as critical as ensuring that knowledge transfer activities are executed as planned. Releasing the resources and planning for a project completion celebration can be done after knowledge transfer has been completed. Holding a steering committee meeting to inform them of the project completion can also be done after knowledge transfer has been completed. Marking the product backlog completion status and updating the communications management plan can be done at any time during the closing process."
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Lucky_Cindy
6 months agovictory108
8 months, 1 week agoSteAle
9 months, 3 weeks ago