Question #: 399
Topic #: 1
[All PMP Questions]

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures.
What should the project manager do to help avoid this situation in the future?

  • A. Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace.
  • B. Replace junior team members with more experienced ones, and negotiate the project scope to compensate for the budget gap.
  • C. Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan.
  • D. Review the velocity of the team over the last several sprints and adjust the plan accordingly.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: D
D. Review the velocity of the team over the last several sprints and adjust the plan accordingly
upvoted 1 times
...
victory108
9 months ago
Selected Answer: D
D. Review the velocity of the team over the last several sprints and adjust the plan accordingly
upvoted 1 times
...
SteAle
10 months, 2 weeks ago
Selected Answer: D
D. Review the velocity of the team over the last several sprints and adjust the plan accordingly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...