An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures. What should the project manager do to help avoid this situation in the future?
A.
Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace.
B.
Replace junior team members with more experienced ones, and negotiate the project scope to compensate for the budget gap.
C.
Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan.
D.
Review the velocity of the team over the last several sprints and adjust the plan accordingly.
D. Review the velocity of the team over the last several sprints and adjust the plan accordingly.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Lucky_Cindy
6 months, 3 weeks agovictory108
9 months agoSteAle
10 months, 2 weeks ago