Question #: 424
Topic #: 1
[All PMP Questions]

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts.
What should the project manager do in this situation?

  • A. Work to understand the key stakeholder's concerns and provide feedback in regular project status reports
  • B. Arrange an ad hoc meeting to address the key stakeholder's concerns with team members
  • C. Reinforce with the key stakeholder that the project is performing on schedule
  • D. Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
xcjxcj
10 months, 2 weeks ago
Selected Answer: B
B. Arrange an ad hoc meeting to address the key stakeholder's concerns with team members
upvoted 3 times
...
victory108
1 year, 2 months ago
Selected Answer: A
A. Work to understand the key stakeholder's concerns and provide feedback in regular project status reports
upvoted 3 times
...
SteAle
1 year, 4 months ago
Selected Answer: A
A. Work to understand the key stakeholder's concerns and provide feedback in regular project status reports
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...