exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 432 discussion

Actual exam question from PMI's PMP
Question #: 432
Topic #: 1
[All PMP Questions]

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule.
What should the project manager do first?

  • A. Assign the tasks to another resource, and ask the resource to work double shifts
  • B. Update the schedule to reflect the project's changes in duration
  • C. Ask human resources (HR) for a replacement, and update the risk register
  • D. Update the resource management plan and resource allocation chart accordingly
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jazzuuu
1 month, 1 week ago
Selected Answer: B
B. Update the schedule to reflect the project's changes in duration Explanation: The first step a project manager should take upon learning about a key resource's unavailability is to update the project schedule to understand the impact on timelines. This allows for proper analysis and decision-making regarding resource adjustments, risk management, or stakeholder communication. A jumps into action without assessing the impact or feasibility. C is a possible next step but should come after analyzing the schedule impact. D is more about documentation and should follow once a new plan is made.
upvoted 1 times
...
victory108
10 months ago
Selected Answer: D
D. Update the resource management plan and resource allocation chart accordingly
upvoted 1 times
...
SteAle
11 months, 3 weeks ago
Selected Answer: D
D. Update the resource management plan and resource allocation chart accordingly
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...