Question #: 444
Topic #: 1
[All PMP Questions]

A client is structured as a matrix organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization.
How should the project manager handle the different stakeholders?

  • A. All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders
  • B. Because there are different perspectives, perform a stakeholder analysis and act based on the outcome
  • C. The project manager is working on the client's premises, so follow the directions of all the key stakeholders
  • D. This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months, 2 weeks ago
Selected Answer: B
B. Because there are different perspectives, perform a stakeholder analysis and act based on the outcome
upvoted 1 times
...
SteAle
10 months, 1 week ago
Selected Answer: B
To manage any stakeholders, a PM needs to analyse them first
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago