A project manager is leading a project which shows a trend to exceed the cost baseline.
What should the project manager do first to manage the budget?

  • A. Ask the project sponsor for assistance in getting the budget back on track
  • B. Meet with the project team to analyze the actual cost to determine deviations
  • C. Inform the stakeholders that the project will be finished over budget
  • D. Issue a change request including the analysis to increase the budget
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SaraJ996
3 months, 3 weeks ago
Selected Answer: B
I believe at first we should find the cause of the problem
upvoted 1 times
...
victory108
8 months, 3 weeks ago
Selected Answer: B
B. Meet with the project team to analyze the actual cost to determine deviations
upvoted 1 times
...
SteAle
10 months, 1 week ago
Selected Answer: B
B. Meet with the project team to analyze the actual cost to determine deviations
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago