What is a tailoring consideration for the application of Project Risk Management processes?

  • A. Project complexity
  • B. Procurement criteria
  • C. Communication technology
  • D. Knowledge management
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
2 days, 10 hours ago
Selected Answer: A
Why the other options are incorrect: B. Procurement criteria ❌ Related to Procurement Management, not Risk Management specifically. C. Communication technology ❌ A tailoring consideration for Project Communications Management, not Risk Management. D. Knowledge management ❌ Related to Project Integration or Resource Management, not a primary tailoring factor for Risk Management.
upvoted 1 times
...
041ba31
12 months ago
Selected Answer: A
A. Project complexity One of the key tailoring considerations for the application of Project Risk Management processes is the complexity of the project. Project complexity can significantly impact the way risk management processes are applied and customized to suit the project's unique characteristics. For example, in a highly complex project, more extensive risk identification, analysis, and response planning may be required. Additionally, the risk management approach may involve a broader range of stakeholders and require more sophisticated risk assessment techniques. On the other hand, for less complex projects, a simpler and more streamlined approach to risk management may suffice. Tailoring the risk management processes based on the project's complexity helps ensure that resources are allocated appropriately and that the risk management efforts are commensurate with the project's specific needs and challenges.
upvoted 1 times
...
alex903
1 year, 5 months ago
A. 6th edition book. pg. 400
upvoted 2 times
...
Khuz07
1 year, 5 months ago
The correct answer is B. PMBOK guide p 506. Tailoring considerations for Project Stakeholder Engagement are: Stakeholder Diversity, Complexity of Stakeholder Relationships, and Communication Technology.
upvoted 1 times
garlicbread
1 year, 4 months ago
That's stakeholder engagement, question is about risk management
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...