exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 528 discussion

Actual exam question from PMI's PMP
Question #: 528
Topic #: 1
[All PMP Questions]

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing.
What should the project manager do?

  • A. Conduct an expert judgment evaluation.
  • B. Review the quality management plan
  • C. Update the lessons learned register
  • D. Review the risk management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Schwery
4 months, 3 weeks ago
Selected Answer: B
Correct Answer: B. Review the quality management plan The quality management plan will help the project manager confirm the labeling requirements and determine why they were not met. This is the first step to resolving the issue and ensuring compliance.
upvoted 1 times
...
hoomz
9 months ago
Selected Answer: D
If an identified risk materializes (such as the regulatory labels being missed), the risk response plan within the risk management plan should already outline the actions to be taken. This includes the immediate steps to address the issue, who is responsible, and any budget or schedule implications. Therefore, while reviewing the quality management plan is necessary to address the immediate quality lapse, reviewing the risk management plan is equally important because it should contain the predetermined risk responses for such scenarios. If a response strategy is already documented for this specific risk in the risk management plan, the project manager should follow that prescribed response. This course of action aligns with the PMBOK 7th Edition’s emphasis on a dynamic and adaptive project management approach, where planning and execution are responsive to changes and new information. The project manager should utilize the risk management plan to execute the appropriate response actions swiftly and effectively.
upvoted 1 times
...
UppersquareCapital
10 months, 3 weeks ago
Can someone please explain to me why it is not D?
upvoted 1 times
UppersquareCapital
10 months, 2 weeks ago
I get it now. Answer is B. In a situation where production is stopped due to missing regulatory labels during an inspection, the project manager should review the quality management plan (option B). The quality management plan outlines the processes and procedures for ensuring that the project meets its quality requirements, including compliance with regulations. By reviewing the quality management plan, the project manager can identify any gaps or deficiencies in the current processes related to regulatory compliance. This will help in understanding what went wrong, why the regulatory labels were missing, and how to address the issue to resume production in compliance with regulations.
upvoted 1 times
...
...
victory108
1 year, 2 months ago
Selected Answer: B
B. Review the quality management plan
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: B
QCP includes procedures describing how to deal with non-conformance issues
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago