A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data. Some external stakeholders are reluctant to provide support.
What approach should the project manager take?

  • A. Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project
  • B. Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
  • C. Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk
  • D. Host a project team meeting, then update the risk register and the project management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: B
because PM do NOT have any reference data so first thing PM need collect info from stakeholder such as project constrain, assumption, critical input for this project
upvoted 2 times
...
victory108
1 year, 8 months ago
Selected Answer: B
B. Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
upvoted 1 times
...
SteAle
1 year, 10 months ago
Selected Answer: B
From the question, it seems that the project is in the initiating phase and the project manager needs to develop the project charter as well as assumption log to capture assumptions & constraints.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...