A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.
What should the project manager do?
A.
Implement the communication tools used by other project teams.
B.
Escalate the issue to the sponsor and ask them to decide.
C.
Inform the project team to continue using the current tools.
D.
Discuss this with the project team and select the appropriate tools.
D because it makes the most sense. Doesn’t need to be escalated, you want to use what works for this teams diversity specifically, and efficiency is cost and the goal is to keep cost down so keeping the same tool is not recommended.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
7 months agoJune_buggy
9 months, 3 weeks ago