Actual exam question from PMI's PMP
Question #: 681
Topic #: 1
[All PMP Questions]

A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.

What should the project manager do?

  • A. Implement the communication tools used by other project teams.
  • B. Escalate the issue to the sponsor and ask them to decide.
  • C. Inform the project team to continue using the current tools.
  • D. Discuss this with the project team and select the appropriate tools.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: D
D. Discuss this with the project team and select the appropriate tools
upvoted 1 times
...
June_buggy
9 months, 3 weeks ago
D because it makes the most sense. Doesn’t need to be escalated, you want to use what works for this teams diversity specifically, and efficiency is cost and the goal is to keep cost down so keeping the same tool is not recommended.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago