A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

  • A. Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.
  • B. Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.
  • C. Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.
  • D. Encourage the sponsor to start another project for the additional location so that the current project is not impacted.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Aymen1989
6 months, 2 weeks ago
We cant change project artifacts Answer C
upvoted 1 times
...
victory108
8 months ago
Selected Answer: B
B. Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project
upvoted 1 times
...
SteAle
10 months ago
Selected Answer: B
I am torn between A and B. It is a bit confusing. According to the PMBOK, you do not need to go for a CR until the scope baseline gets approved. From the question, it seems that we are still in the initiation phase with the charter being just approved. However, without analyzing the impact, how can the PM ask the sponsor to increase the budget & timeline
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...