exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 631 discussion

Actual exam question from PMI's PMP
Question #: 631
Topic #: 1
[All PMP Questions]

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

  • A. Continuously communicated the changes in the work plan and the agreement to the client
  • B. Defined acceptance criteria in a quality checklist agreed upon before starting the build phase
  • C. Provided compensation for issues due to the variance in the agreed-upon requirements
  • D. Approved a detailed change management process before starting the build phase
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months, 1 week ago
Selected Answer: B
B. Defined acceptance criteria in a quality checklist agreed upon before starting the build phase
upvoted 1 times
...
SteAle
9 months, 1 week ago
Selected Answer: B
PMBOK: "Quality checklists should incorporate the acceptance criteria included in the scope baseline."
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago