A project manager prepared a project benefits management plan.

Which of the following should be included in this document?

  • A. Strategic alignment, benefits owner, risk register
  • B. Target benefits, benefits owner, lessons learned
  • C. Project requirements, target benefits, issue log, metrics
  • D. Target benefits, strategic alignment, time frame for realizing benefits
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months, 1 week ago
Selected Answer: D
D. Target benefits, strategic alignment, time frame for realizing benefits
upvoted 1 times
...
SteAle
9 months, 1 week ago
Selected Answer: D
D. Target benefits, strategic alignment, time frame for realizing benefits (PMBOK - 1.2.6.2 PROJECT BENEFITS MANAGEMENT PLAN
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel