exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 17 discussion

Actual exam question from PMI's PMI-RMP
Question #: 17
Topic #: 1
[All PMI-RMP Questions]

A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low.
What is the first step that should be taken?

  • A. Review the project schedule and recommend fast tracking the schedule and/or crashing the critical path.
  • B. Discuss the project schedule with the executive sponsor and agree on a strategy for updating the risk management plan and risk response plans.
  • C. Update existing risk response plans and include more resources to get the project back on track.
  • D. Immediately call a steering committee meeting, report the project status, and suggest project scope reductions to save time.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
yandasatria
9 months ago
Selected Answer: B
By discussing the project schedule with the executive sponsor, the project manager can share the findings from the risk analysis and highlight the schedule's shortcomings. Together with the executive sponsor, they can determine a strategy for updating the risk management plan and risk response plans to address the schedule issues and mitigate potential risks.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago