After a meeting with the customer, the project manager receives special recognition because the project is always on schedule. Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.
What should the project manager do in the project team meeting?

  • A. Share the customer feedback with the project team
  • B. Follow the meeting agenda and make a list of the next deliverables
  • C. Document this feedback in the meeting minutes
  • D. Start planning how to improve the dates of next deliverables
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months, 1 week ago
Selected Answer: A
A. Share the customer feedback with the project team
upvoted 1 times
...
miggykurkova
8 months, 1 week ago
In order to motivate team, share recognition
upvoted 2 times
...
kevindebruyne
9 months, 1 week ago
Selected Answer: A
A. Share the customer feedback with the project team The information is also motivate the team
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago