A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed.

Which technique should the project manager apply to verify the knowledge transfer?

  • A. Regression analysis
  • B. Meetings
  • C. Expert judgment
  • D. Brainstorming
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Scottxk1
Highly Voted 1 year, 2 months ago
Honestly, none of these are effective knowledge transfer techniques. I cannot pick one as they don't actually do anything. Training, Shadowing, Mentoring, Documentation of design, user guides, Q&A's, all of these are better than what is listed here.
upvoted 5 times
...
Abdelmonm
Most Recent 9 months ago
Selected Answer: B
Conducting meetings is a common technique for verifying knowledge transfer. In this context, the project manager can organize a meeting with relevant stakeholders, including members of the operations team, to confirm that the necessary knowledge has been transferred successfully. This provides an opportunity for team members to discuss and address any remaining questions or concerns and ensures that there is a shared understanding of the project's deliverables and the ongoing support requirements.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: B
B. Meetings
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: B
By involving all stakeholders(diverse group) in a meeting, the project manager can obtain a comprehensive perspective on the knowledge transfer's success. This approach ensures that multiple viewpoints are considered, providing a more well-rounded evaluation of the effectiveness of the transfer to the operations team. Where as Expert judgement will only consider opinion of SMEs.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago