exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 280 discussion

Actual exam question from PMI's PMP
Question #: 280
Topic #: 1
[All PMP Questions]

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.
What should the project manager do?

  • A. Initiate regular conference calls with the vendor for status updates to keep this item in focus.
  • B. Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.
  • C. Assess the schedule impact and evaluate the most feasible solution to keep the project on track.
  • D. Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
HYEmily
3 months ago
Selected Answer: C
C. Assess the schedule impact and evaluate the most feasible solution to keep the project on track.
upvoted 1 times
...
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: C
C is the best answer
upvoted 1 times
...
victory108
9 months, 2 weeks ago
Selected Answer: C
C. Assess the schedule impact and evaluate the most feasible solution to keep the project on track
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago