A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion. What should the project manager do?
A.
Initiate regular conference calls with the vendor for status updates to keep this item in focus.
B.
Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.
C.
Assess the schedule impact and evaluate the most feasible solution to keep the project on track.
D.
Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.
C. Assess the schedule impact and evaluate the most feasible solution to keep the project on track
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
HYEmily
3 months agoLucky_Cindy
6 months, 3 weeks agovictory108
9 months, 2 weeks ago