exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 454 discussion

Actual exam question from PMI's PMP
Question #: 454
Topic #: 1
[All PMP Questions]

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control. The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer.
What should the project manager do?

  • A. Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve
  • B. Develop the quality management plan, as quality is as equally important as cost and schedule management
  • C. Get confirmation from management that the team member has enough experience to build software without quality control
  • D. Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
d67fcef
2 months, 3 weeks ago
Selected Answer: B
This action comes before communication plans.
upvoted 1 times
...
tonybuivannghia
9 months, 4 weeks ago
Selected Answer: B
B. Develop the quality management plan, as quality is as equally important as cost and schedule management
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: B
B. Develop the quality management plan, as quality is as equally important as cost and schedule management
upvoted 1 times
...
800405
1 year, 9 months ago
Developing a quality management plan is necessary, as quality is as equally important as cost and schedule management
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel