Question #: 410
Topic #: 1
[All PMP Questions]

A company is implementing a new system. The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies. The product owner is confused as to how to start delivering the functionalities required.
How should the project manager assist the product owner?

  • A. Coach the product owner on how to create a product backlog.
  • B. Discuss the product owner's responsibilities within the project team.
  • C. Encourage the team to subdivide the project tasks.
  • D. Create a work breakdown structure (WBS) and explain the deliverables to the product owner.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: A
A. Coach the product owner on how to create a product backlog
upvoted 2 times
...
victory108
9 months ago
Selected Answer: A
A. Coach the product owner on how to create a product backlog
upvoted 2 times
...
Aish_
9 months, 1 week ago
Selected Answer: A
coaching the product owner on creating a product backlog (option A) is more specific to the situation described and directly addresses the product owner's confusion about how to start delivering the functionalities required using Scrum and Kanban methodologies.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...