Actual exam question from PMI's PMP
Question #: 395
Topic #: 1
[All PMP Questions]

A project team has recently completed the initial sprint for developing an automated payroll system for a company. The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next.
Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two.)

  • A. Company mission and vision
  • B. Sprint goal
  • C. Sprint charter
  • D. Product backlog
  • E. Burndown chart
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 month ago
Selected Answer: BD
DB .. no other choices
upvoted 1 times
...
Kim222
8 months, 1 week ago
Selected Answer: BD
A sprint charter is generally not required.
upvoted 1 times
...
Lucky_Cindy
1 year, 6 months ago
Selected Answer: BD
Spring goal and product backlog
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: BD
B. Sprint goal D. Product backlog
upvoted 2 times
...
AYZ
1 year, 8 months ago
It should be "Sprint goal" and "Product Backlog". Simple approach is to look what is the required goal of sprint and see what are the requirements available in Product Backlog.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago