Question #: 215
Topic #: 1
[All PMI-ACP Questions]

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

  • A. Address this impediment by obtaining suitable training for the team.
  • B. Address the risks resulting from complexity within sprint zero.
  • C. Facilitate team brainstorming of the risks resulting from complexity for the risk register.
  • D. Motivate the team to try new technical approaches.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ImGonnaPassIt
10 months, 1 week ago
Selected Answer: C
C - discover risks then B - sprint zero. I vote C.
upvoted 2 times
...
melki_zedek
1 year ago
Selected Answer: B
B, Sprint Zero is more agile. During the sprint zero phase, the team can identify and mitigate potential risks associated with the project's technical complexities.
upvoted 1 times
...
Petrevski
1 year, 3 months ago
Selected Answer: C
C = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...