exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 376 discussion

Actual exam question from PMI's PMP
Question #: 376
Topic #: 1
[All PMP Questions]

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?

  • A. Ignore the unclear requirements and focus on the delivery plan of the project.
  • B. Wait for the requirements to be more clear before any further action is taken on the project.
  • C. Break down the requirements and prioritize the requirements into iterative work packages.
  • D. Escalate the issue of unclear requirements to the management team and wait for final authorization.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: C
C. Break down the requirements and prioritize the requirements into iterative work packages
upvoted 1 times
...
kevzzz
7 months, 1 week ago
Selected Answer: C
You're hired as a project manager. Leaders lead and you are a hybrid kind of PM. Take this opportunity to introduce the hybrid approach since there is uncertainty involved.
upvoted 2 times
...
ali514
8 months, 3 weeks ago
Selected Answer: C
Since it is a hybrid we can use iterative here
upvoted 2 times
...
victory108
9 months ago
Selected Answer: C
C. Break down the requirements and prioritize the requirements into iterative work packages
upvoted 2 times
...
Goku_PMP
9 months, 1 week ago
Selected Answer: B
when the focus of company is predictive only, how I can use hybrid approach??? its better to wait to get clear requirements.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...