Exam PMP topic 1 question 569 discussion

Actual exam question from PMI's PMP
Question #: 569
Topic #: 1
[All PMP Questions]

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?

  • A. Escalate to the management team to increase the timeline based on the complexity of the project
  • B. Wait for the other project estimates before planning the schedule
  • C. Prioritize and estimate the milestones for the high-level requirements based on historical data
  • D. Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: C
Should focus on the question to answer. The question is the PM need to preparing for next step so I eleminate B,D. For A, PM should not escalet problem due to project dependency
upvoted 1 times
...
mesacgon
1 year, 5 months ago
Yo creo que B.
upvoted 1 times
...
certificate988
1 year, 5 months ago
Selected Answer: B
'The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain ' -> This means priorities can't be decided for the requirements and milestones have zero duration(estimation is invalid). -> PMO does not have job to estimate tasks for all projects. -> So, only option is B to wait for dependent project estimate.
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: C
C. Prioritize and estimate the milestones for the high-level requirements based on historical data
upvoted 2 times
...
Jamrock
1 year, 9 months ago
Selected Answer: C
C. Prioritize and estimate the milestones for the high-level requirements based on historical data
upvoted 2 times
...
PeterTheTree
1 year, 9 months ago
Selected Answer: D
D. Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan. This might be the best approach, as the PMO would typically have an overview of all projects within the program and be in a position to coordinate and manage interdependencies. They can help ensure that the project plans for all projects are aligned and take into account the interdependencies. In conclusion, the best approach for the project manager in this situation would likely be option D. Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan. This approach ensures that all interdependencies are managed at a program level, reducing the risk of conflicts and delays.
upvoted 2 times
adingmaki
1 year, 7 months ago
Then what's left of your job as a PM? You basically gave them everything.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.