exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 560 discussion

Actual exam question from PMI's PMP
Question #: 560
Topic #: 1
[All PMP Questions]

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
What should the project manager do?

  • A. Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority
  • B. Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities, share this with all stakeholders, and ask the team to complete their tasks as scheduled
  • C. Conduct a general meeting with all stakeholders and review and address a list of activities for each of them
  • D. Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: D
client raise concern and disaggree so PM need to identify the root causes first
upvoted 1 times
...
DavidTri
10 months, 2 weeks ago
Selected Answer: D
first thing is need to indentify & understanding the issue
upvoted 1 times
...
Rajki
1 year, 3 months ago
Selected Answer: D
D is the correct answer
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: D
D. Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities
upvoted 2 times
...
Jamrock
1 year, 9 months ago
Selected Answer: D
Best answer of them all that addresses the issue on disagreement.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...