A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

  • A. Specialized reports created specifically for the meeting as per directions from the project sponsor.
  • B. Potential changes to the project's strategy and the feedback from senior executives.
  • C. The deliverables that are performing well and those that need more work.
  • D. Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Trytrio
8 months, 4 weeks ago
Selected Answer: D
D but that "regulations" are mentioned is really confusing.
upvoted 1 times
...
6thEditionAndy
11 months ago
Selected Answer: D
In theory D, in practice A. If the project sponsor requests a specific information and you show up with other information, your PM career at that firm is short-lived
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: D
D. Metrics and KPIs are objective measures that can give a clear picture of the status of project deliverables. This allows senior executives to make informed decisions and provide appropriate guidance. Additionally, if there are regulatory requirements, the KPIs can also indicate how well the project is aligning with those requirements.
upvoted 3 times
...
victory108
1 year ago
Selected Answer: D
D. Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables
upvoted 1 times
...
Jamrock
1 year, 2 months ago
Selected Answer: D
Reviewing metrics and key performance indicators (KPIs) that objectively reflect the status of project deliverables is the most effective approach during a management review with senior executives. It provides a data-driven assessment of the project's execution and progress.
upvoted 1 times
...
TonyMontana_
1 year, 2 months ago
Selected Answer: B
B. Potential changes to the project's strategy and the feedback from senior executives.This will help ensure that the project's direction aligns with the organization's goals and that any adjustments needed are considered based on the input of senior executives.
upvoted 1 times
Jamrock
1 year, 2 months ago
B. is the worst answer of the 4 options.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago